energyNP.com  
Tel
98510-91900 
Email

Er.energyNP@Gmail.com

        energyNP@hotmail.com
Menu

 
 
News  
Back to energy news list >>>
 

 
 
 Air Conditioner
 Battery
 Booster Pump
 Charger
 Cold Storage Room
 Electric Power Tools
 Electric Water Heater
 Garbage Disposal
 Station
 Generator
 Heat Pump
 Inverter
 Lead Acid Battery
 LiFePO4 Battery
 Power Supply
 Rectifiers
 Self Priming Pump
 Solar Energy
 Solar Water Heater
 Transformer
 Treadmill
 UPS
 Voltage Stabilizer
 Wind Energy

 
Portable Electric Car Charger | Portable EV Charger | Portable Charger for Home Use | Charging Station for Home Use | Kathmandu Nepal
 
Electric Folded Treadmill Nepal Kathmandu
 
Gree Air Conditioner Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 

 

 
  69 MW Marsyangdi Hydropower plant resumes electricity generation

The 69-megawatt Marsyangdi Hydropower Station has resumed electricity generation after completing a comprehensive maintenance and repair program that required a full shutdown of the plant for 21 days.

Located in Aanbukhaireni Rural Municipality, the hydropower facility restarted operations following the successful completion of complex technical and civil engineering works aimed at strengthening key infrastructure and improving long-term operational reliability.

According to the Nepal Electricity Authority (NEA), the plant had been completely shut down to carry out large-scale maintenance and rehabilitation activities that had been pending for years. The works were completed within the scheduled timeframe, allowing electricity generation to resume without delay.

One of Nepal’s Largest Hydropower Stations

Among hydropower plants operated by NEA, the Marsyangdi facility ranks as the third largest in installed capacity and the second largest in annual electricity production.

During the last fiscal year 2081/82 BS (July 16, 2024 – July 15, 2025 AD), the plant generated 451.7 gigawatt hours (GWh) of electricity, making it a critical contributor to Nepal’s national power supply.

In the current fiscal year 2082/83 BS (July 16, 2025 – July 15, 2026 AD), the plant had already produced 293.5 GWh of electricity by the end of Magh 2082 BS (mid-February 2026 AD) before the maintenance shutdown was initiated.

To ensure sustainable long-term operation, the plant was taken offline beginning Falgun 2, 2082 BS (February 14, 2026 AD) to carry out major repair and rehabilitation works.

Major Structural Repairs Completed

Plant chief Kapildev Manjan said the shutdown period was used to complete several technically challenging works that had remained unresolved for years.

One of the most critical tasks involved strengthening civil structures near the dam area. The upper riverbank near the dam and sections around the desander structure had experienced erosion that posed potential risks to plant infrastructure.

Repair and reinforcement works were carried out to protect these structures and ensure long-term stability of the hydropower facility.

Under-Sluice Gate Restored After 14 Years

A major milestone of the maintenance program was the restoration of the under-sluice gate, a key hydraulic component designed to prevent sand and sediment from entering the water conveyance tunnel.

According to plant officials, the structure had remained non-functional for approximately 14 years due to structural damage.

Engineers successfully repaired the damaged components during the shutdown, making the system operational again. The restoration is expected to significantly reduce sediment intrusion into the tunnel system, which has historically posed a major operational challenge for Himalayan hydropower projects.

Sediment Removal and Mechanical Overhaul

Another important activity completed during the maintenance period was the removal of sand deposits that had accumulated for years in the compensating basin located near the main intake structure.

Excessive sediment accumulation can reduce water flow efficiency and affect turbine performance, making sediment management a critical maintenance priority for run-of-river hydropower plants like Marsyangdi.

Plant chief Manjan said several previously stalled contracts and mechanical repair tasks were also completed during the shutdown period.

“We prioritized long-pending contractual works and mechanical repairs to ensure the plant’s reliability,” he said.

Overhauling of Unit No. 3

Technicians also conducted a full overhaul of generating Unit No. 3, one of the plant’s key turbine-generator units.

The maintenance work was carried out by in-house engineers and technicians from the Marsyangdi plant along with technical staff mobilized from other hydropower stations under NEA.

This collaborative technical approach allowed the utility to complete the overhaul efficiently while minimizing operational costs.

Round-the-Clock Civil Works at Dam Site

Civil engineering works at the dam site were carried out under a 24-hour work schedule, with labor teams deployed in three shifts to ensure timely completion of the repairs.

According to plant management, the shutdown was strategically scheduled during a period when river discharge levels were at their lowest, minimizing the impact on electricity generation and the national power supply.

“We planned the maintenance work during a period of minimal river flow so that the reduction in electricity production would be limited,” Manjan explained.

Coordinated Effort Across NEA Departments

Officials credited the successful completion of the project to strong coordination among NEA’s central offices, departmental units, and regional directorates.

Support from senior management allowed engineers to address several critical civil works that had remained pending for years due to technical complexity and logistical challenges.

Electrical System Upgrades

In addition to structural and mechanical repairs, the maintenance program also included electrical upgrades within the powerhouse.

Among the works completed was the replacement of LT-type breakers, along with other necessary electrical and mechanical maintenance tasks designed to improve operational safety and reliability.

Plant officials said the completed maintenance and upgrades are expected to enhance electricity generation efficiency while reducing technical risks associated with aging infrastructure.

Importance for Nepal’s Hydropower Sector

The Marsyangdi Hydropower Station is one of Nepal’s most strategically important state-owned hydropower plants, playing a vital role in stabilizing the country’s electricity supply, particularly during the dry season.

With hydropower accounting for the overwhelming majority of Nepal’s electricity generation, ensuring the reliability of major plants like Marsyangdi is essential for maintaining grid stability and meeting growing national energy demand.

The successful completion of the 21-day maintenance shutdown is expected to strengthen the plant’s operational performance and extend the lifespan of critical infrastructure within one of Nepal’s key hydropower assets.

[ 12 March 2026 / fiscalnepal.com ]   
 

Lithium Iron Phoaphate (Lifepo4) Battery - Wall Mounted Energy Storage Lithium Battery - Nepal - Kathmandu

 SYSTEM
 Backup System
 Solar System
 Wind Power System
 Heating System

 AC & Ventilation
 System

 Cold Room System
 Charging System
 for
 Telecom/Industry
 Substation System

 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Energy - Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries